Things continue to progress forward over here at the josbite! Masons quickly got to work laying the first two courses of foundation CMU block in anticipation of the first portions of the slab turndown being poured later this week. From there they will install scaffoling and work their way up in the apparatus bay where the future fire engines will be parked!

Electrical and Plumbing underground crews continued running their conduits and pipes respectively. Electricians, specifically, ran conduits to the electrical room and are currently working on the pathways towards the generator and transformer.

Lastly, we got started on building our mock up panel! This will give us a sneak peak at how the finishes of the project will look and allow our design teams to ensure that all materials work together cohesively.