4.17.25 UpdateTown of Matthews, We have officially come to the end of this journey and this will be our final update! The building is complete, the landscaping is in bloom, and Station 3 has been fully operational for a few weeks now. Below, please see some...
3.10.25 Update
3.10.25 UpdateJust wanted to pop in with a quick update to share with the town that we received final Certificate of Occupancy for the metal storage building! We also have the electric vehicle gate operating and the masonry portions of the monument sign are...
3.3.25 Update
3.3.25 UpdateHappy Monday! The Samet Team is working on finishing touches on the Fire Station and things are so close to being finished! The Fire Department has continued to move in furniture and its been exciting to see some of the spaces come to life. All final...
2.10.25 Update
2.10.25 UpdateHappy February! We just wanted to pop in with a quick little update to share that we received our Temporary Certificate of Occupancy in early January! This means we have been able to make strides towards a Final Certificate of Occupancy and that the...
1.03.25 Update
1.03.2025 UpdateTown of Matthews, Happy 2025! We hope you all had a wonderful holiday season. It has been a minute since we last update you so we have a lot to share! If you've been passing by you will have noticed that things are really coming together onsite....
10.25.24 Update
10.25.24 UpdateHello, all! Hard to believe that it is almost Halloween! The jobsite has been buzzing through the month of October and the Fire Station is looking beautiful! On the exterior, brick is completely finished and siding is installed and we are almost...
9.13.24 Update
9.13.24 UpdateHappy Fall, Town of Matthews! It has been a minute since we updated you on the project and things have really been moving along nicely onsite. Below are some updates we've been busy onWe were able to pour the concrete slab for the apparatus bay after...
8.5.24 Update
West Side Slab on Grade Start of East Side Framing View of Building Front View of Roof Sheathing on East Side and Apparatus Bay West Side Prepped for Slab Pour East Side Framing View of Building from East Corner Mobile Crane Setting Trusses West Side Framing...
7.12.24 Update
7.12.24 UpdateThe jobsite has been busy the past couple of weeks! As of yesterday the CMU walls for the apparatus bay are FINISHED! The steel arches were installed above the openings for the overhead garage doors late last week and they look amazing. This is going to...