MATTHEWS FIRE STATION #3

News

6.24.24 Update

6.24.24 Update

6.24.24 UpdateA lot has happened here at the Matthews Fire Station #3 project since our last check in! Our masonry team is making rapid progress on the CMU block walls that make up the apparatus bay that will house the future fire engines! They are close to a height...

6.11.24 Update – CMU Block Begins

6.11.24 Update – CMU Block Begins

6.11.24 Update - CMU Block BeginsThings continue to progress forward over here at the josbite! Masons quickly got to work laying the first two courses of foundation CMU block in anticipation of the first portions of the slab turndown being poured later this week. From...

6.4.24 Update – Foundations Poured

6.4.24 Update – Foundations Poured

6.4.24 Update - Foundations PouredWe are excited to share that all of the foundations have been poured as of Friday, 5/31/24! Footings were dug and rebar was tied and placed within them throughout the week. Concrete trucks arrived onsite Friday for the pour. While...

Start of Construction

Start of Construction

Start of ConstructionMatthews Residents, we are excited to kick off our regular project updates, in order to keep you 'in the know' on the progress of the new Matthews Fire Station #3. The Samet team has been onsite for a handful of weeks prepping for the exciting...

Project Update: Clearing and Prepping the Site

Project Update: Clearing and Prepping the Site

Project Update: Clearing and Prepping the SiteWelcome to everyone to our first project update. Thanks for stopping by to see what's happening at the site. Right now we're in the early stages of the project. We've demoed the existing structure on the property and we...